Okaya Power Group successfully commissions 100 KWp Hybrid Solar plant in Baddi, Himachal Pradesh at its manufacturing unit which will generate more than 144 Mwh energy annually reducing its power consumption from the grid to 40%.
The commissioned hybrid solar plant makes the unit self-sufficient for its daily energy requirement and also supports the uninterrupted production process with continuous power supply even in the scenario of unanticipated power cuts happening due to grid failure.
The capacity of Okaya’s hybrid solar plant is 100 KWp with 306 number of 330Wp modules, 250 Kw Power Conditioning System (PCS) and 250 kwH Li ion battery energy storage with Battery Management System (BMS). The efficient BMS ensures the battery performance with proper safety measures within a system and Battery Energy Storage System (BESS) will be able to manage energy requirements as per application in addition to backup support, load sharing, energy shifting, etc.